projected_completed

 

Oil & Gas / Mining Sector / Process Plant Sector / Port Material Hadling / Equipment / General Construction / Steel Bridging

 

Ujung Pangkah Offshore Phase II WHP-EPC

 

jack_top

Project Details


Location        : Ujung Pangkah, Gresik - Indonesia

Scope            : Oil & Gas

Description  : Ujung Pangkah Offshore Phase II WHP-EPC

Client : HESS Ujung Pangkah Ltd

 

Project History

 

HESS Ujung Pangkah

First Production : 2007
HESS Interest : 75% operator
Partner : KUFPEC (25%0


The Pangkah PSC,located off the northeast cost of Java, was sign in 1996. It is operated by HESS under the Pangkah Production

Sharing Contract with the Indonesian Government. Pangkah began producing gas in 2007, supplying power generation needs in the region.

Oil production from a second phase of development began in late. LPG production, also part of the Phase 2 development, commenced in 2009.

 

In March 2008, HESS (Indonesia-Pangkah) signed a contract with PT. Bakrie Construction for Engineering, Procurement, Construction &

Commissioning (EPCC) of our offshore Pangkah Field Development Wellhead Platform B (WHP-B). This Platform is a 20 Slot wellhead platform

designed for the jackup rig, tender assist drill rig, or self contained platform dril rig. Process equipment includes test seperator, two phase

production separator, gas lift knockout vessel, with significant of piping and instrumentation. The Platform has an MMC control room with control

and communication equipment. Topsides weight is approximately 1600 tonnes. The jacket is an eight legged steel substructure weighing

appriximately 360 tonnes. eight steel piles designed for penetration of 108 meters  weighing approximately 1260 tonnes.

This Platform is a key production hub for HESS offshore oil & gas development.

 

Description

PT. Bakrie Construction completed Jacket & Topside fabrication for HESS Ujung Pangkah Wellhead Platform B at the end of August 2009.

This project has been done tremendously at our yard facility in Sumuranja, Merak - Banten.

We are really proud of this hard-work and full-supported project as it is one of a kind of valuable and important projects in our

experiences and also strengthen our fabrication capability in oil and gas industry.

 

>> Back to Project List <<